Sprint backlog in Scrum is evil

As is defined by Mike Cohn Scrum encourages teams to breakdown stories in the Product Backlog into tasks which are 8-16 hours worth of effort and which become a part of the Sprint Backlog. These are the tasks which the team commits to completing at the end of a Sprint (which can be 2-4 weeks).

The problem with breaking a good user story into tasks like "Create the UI", "Develop the Service", "Test the Service" etc... and maintaining them separately in a backlog , is that it encourages Scrum Masters to allow different people in the team to pick these bits of tasks of a big user story. So a scenario where Bob (and his pair ?) works on the "Create the UI" task and Ron (and his pair? works on "Develop the Service" in parallel, in order to finish work fast is encouraged in the team.

Scrum templates like those proposed by Ken Schwaber, take it even further by asking people to track hours logged on these tasks. Not only is tracking tasks like these unnecessary, but if a developer does not develop a story end to end, he completely misses out the bigger picture of the architecture. This is where a team ends up with UI experts who know only JavaScript/HTML with no clue of the services layer and Services experts who just develop services without knowing their consumers.

To me, a good user story which has business value, is the only unit of work I would like to track. Developer pairs in a team should be encouraged to work on complete user stories so that they understand the architecture end to end , and have the satisfaction of adding business value to the product they are working on. This is extremely important but unfortunately I have seen many adopters of Scrum mislead by popular Scrum literature available.

Sunday, October 25, 2009

Managing Agile team chaos with smaller sub teams

Agile practices work really well when you are dealing with smaller teams. Small teams are bound to be much more efficient and focused. It allows people to know each other well, while having fun at work. Simply put, it reduces the amount of bloat or waste, and it becomes quite evident when you see the team working.
Ideal Size

I prefer a team to be a max of 2-3 developer pairs. Any number more than this calls for a team to be split into smaller sub teams.

Team composition

Ideally based on features or themes. If you have 4 pairs of developers you are bound to be working on more than one theme or feature. A good Business Analyst or a Product Owner should be able to identify these themes in the functionality being developed. If you do not have 2 broad features, try to club the smaller features based on a pattern or a theme. Never split the team based on infrastructure (eg: UI team, Services team)

Align a BA and a QA to be focused on specific themes. If the features are functionally less complex, then a BA and a QA might be shared across these teams.


Split the meetings, making them shorter and more focused

The idea of reducing bloat also applies to the team meetings. Have separate standups among the smaller sub teams. When you have a max of 6-8 people in a standup, everyone will be attentive, interested and will remember what the first person said in the standup when it ends.

Split the Iteration Planning meetings also according to teams which are focused on tasking and estimating features they are developing. You can even have mini retrospectives with sub teams on a regular basis.


Split the card wall

The story card wall tends to clutter up with cards for 6 pairs of developers. Splitting the card wall into separate ones for each sub team helps in keeping the card wall cleaner and motivates the team to keep it up to date.


Handling dependencies across teams.

There will always be dependencies between sub teams. The teams might share some areas in the code base, builds, QA integration boxes etc... A PM or a lead of the whole team plays a vital role here. A PM will have to be part of both the standups regularly and ensure that dependency blockers are removed by teams communicating effectively. As long as the teams are sitting closely, once can always shout out if there is a show stopper !

The whole team can talk about technical dependencies and showstoppers in impromptu developer huddles/technical standups as and when required.


Managing people rotation between teams

People will get bored working on the same feature. Developers will be bored if they were working in a team just fixing bugs or small enhancements. similar is the case with BAs and QAs.Rotation is also important to allow team members to pair with members of the other sub team.

Any rotation between teams can be done at the beginning of an iteration. 1 person swapping in between two 2-pair teams would be ideal. A PM can also choose to limit the number of rotations based on constraints such as knowledge around a particular area of functionality etc...


Better feedback, pair rotation, and self organization

In a 8-10 people team sitting across a table, people can quickly learn about each others strengths and weaknesses. Knowing each other well automatically allows for a better feedback culture within the team. Pair rotation within 4-6 people allows people to pair with everyone in the sub team.

In a small team people have the tendency to self organize themselves. You will see people take on more responsibilities, sometimes a BA playing a PM hat and proactively planning stories for the next iteration. People will not wait for a retrospective to speak their mind about a certain issue, but shout across the table !


Stitching it all together

The Project Manager of the whole team plays a key role in keeping the sub teams focused and on track. For this purpose a PM can conduct an Iteration Close/Planning meeting with the whole team, showing team members where the team stands on velocity, and scope burn down, along with any team rotations for the next iteration. This could be followed by letting the whole team know the scope planned for next iteration.

Needless to say that team outings and other fun activities would involve the whole team !

Tuesday, September 22, 2009

Needless time tracking in Scrum

On a new assignment, while the client is trying to slowly adopt Scrum (and hence Agile), I have been bothered by the needless time tracking that is proposed by some of the Scrum templates and related literature .

Tracking hours remaining at a task level, or even %age task completion to me is useless. Either a user story is done or not done, simply because you cant do much with a half baked story. A story which is done contributes to the velocity or throughput. Everything else is inventory.

Monday, July 13, 2009

Services have business value

When you are on a project which is about evolving a set of services from an existing application, or building from scratch, there is always a lot of talk on the architecture and service governance aspects.

But if you are a Business Analyst on this piece of work, and you are asked to write stories for these services, you will wonder.. "well how can we showcase just services ?". If you have never done this before, you might even conclude that writing stories without a consumer of the service is not such a good idea. A lot of Agilists might argue that having a services story is a bad user story.

This happens because the fact that "Each Service has business value" does not become very apparent. If you look at Amazon WebServices it becomes immediately evident that each of the services have a set of features which can be sold to customers.

Services are a reality in today's world on the web, and people make money by selling services. A story which builds a service to search a book based on ISBN has business value. It does not need to have a pretty front end consumer for you to write a good user story. A temporary client/UI would be sufficient or maybe even functional tests/specs. It is still a good user story. This essence needs to be spread across the entire team, so that BAs and Devs are on the same page on "Good User Stories" for this kind of project.

Both BAs and QAs have to embrace this along with the developers on the team, and look at ways to apply Agile principles considering this, rather than being dogmatic in their approach towards Agile and SOA.

Friday, July 3, 2009

Challenges in applying Theory Of Constraints to Agile Software Development

After finishing Goldratt's first book, the Goal, I immediately jumped to David Anderson's book on Applying TOC in Agile Management. Preetam also has left some interesting comments on my blog on the differences between s/w and manufacturing which should not be neglected.

One important thing which is still puzzling me at this stage is, if you have to account for throughput, how do you measure value. Value here is the value of a story or a feature. If you are a services shop building an application for a customer, it is upto the customer to determine this business value of a story. Quite often this is not easy to determine, specifically for people like Subject Matter Experts you are dealing with to gather your requirements, who do not deal with sales at all.

In a manufacturing plant, if you have signed a contract to deliver 10 cars for say $100,000. The cost of an engine still waiting in the queue (work in progress) is almost equal to the value of 1 car, $10,000. However the similar analogy is not easily applicable to a software development team. If a story is in progress, it cannot be easily translated to how much $$ is part of inventory.The story might be part of a bigger feature. Also, determining the business value for that feature in $$ itself can be tricky

David's book touches upon in-house IT shops providing IT services (eg: SaaS) or implementing a software product. In these cases, revenue from Sales can be directly mapped to what is being developed. Which is what should happen, in order to increase the throughput of the system, and hence increase the revenue. This is not the case when you are providing IT services to other clients (not in-house).

Some might say you can use story estimate (ideal days or points). Again this represents cost and not value. The iterative nature of Agile also makes it difficult to apply the same principles as a manufacturing plant.

While I am still looking for some answers, the learning on how to deal with bottlenecks, optimizing the whole system, and applying the same to software development, from both the books, are still quite useful.